Following the pour of the foundations, the base level of the Stepoc blocks are set true.
The plan is to dry build up the wall on the boundary in at least two stages, with reinforcement added at each steps, and the waterproofing slurry on the exterior added by over-reaching, where the access is too tight for a person to be behind.
Once the Stepoc has been built up, it will be filled with concrete, using a pump, and it will then be strong enough to withstand ground pressure around it.
And here is the Stepoc blockwork finished with scaffold ready for pour of concrete.
Unfortunately no concrete pump is available this week, probably due to trades fortnight, so site work stops and builders go on holiday too.
No comments:
Post a Comment