Foundations for garage - July 2016



Foundations for garage 11-15 July
This week was all about final excavations of garage foundation and constructing steel reinfocement.
Drains and conduits for all services were installed.
Builders used electric tool to cut and bend steel, and excavated the toes with wood frame around them.
Occasional heavy showers later in the week interrupted progress.
Radon/DPM installed over insulation.




Steel reinforcement for concrete raft is set out on DPM, with leads for vertical reinforcement of Stepoc walls, 18-19 July.














The concrete pour commences on 20 July, with severe thunderstorms and weather warnings forecast. Two and a half concrete trucks arrive through the morning, from 1000 to 1230.













And the pour is completed soon after mid-day.